|
AREVA > Home > Publications > Community
Updates > Community
Updates June 2002
Community Updates
McClean Lake and Cluff Lake Projects
June 24, 2002
McCLEAN LAKE
Congratulations to Robert Fern, heavy equipment mechanic apprentice
from Fond du Lac, who has passed his Inter Provincial Journeyman's
exam. Robert is the first COGEMA Resources McClean Lake apprentice
to achieve this goal!
McClean Lake has not had a spill since the last Community Update.
The concentrations of elements contained in the water discharges
from the JEB mill and Sue mine treatment plants during May were
well below the limits set by the regulatory agencies.
CLUFF LAKE
The last ore truck left the Dominique Janine underground mine on
May 31. The DJU mine is now closed. Its entrance ramp and other
openings have been backfilled to within 10 metres of the surface.
Milling will continue to process the remaining ore stockpiles by
the end of the year. The mill is operating on a week-on/week-off
basis.
The CIM John T. Ryan regional safety award was presented to the
Cluff Lake mine at the Saskatchewan Mining Association Mine Rescue
Competition.
Cluff Lake has not had a spill since the last Community Update.
Concentrations of elements contained in the water discharges from
the treatment plant during May were well below the limits set by
the regulatory agencies.
HEAVY HAUL AGREEMENT
The heavy haul agreement between the provincial government and
COGEMA Resources and Cameco is now in its eight year. In that time,
the companies have spent about $9 million on road improvements between
La Ronge and Points North. The agreement allows the companies to
haul weights greater than normally allowed under provincial highway
regulations. In return, a portion of the savings from hauling those
greater amounts is put in a fund and used to improve the road surface.
When the partnership began back in 1994, the projects were directly
linked to improving safety by getting rid of dangerous corners or
hills with poor visibility. With those jobs now complete, work planned
for 2002 includes $1.35 million in road improvements on Highways
102 and 905. To this point, Highways 102 and 905 have been improved
with no additional cost to the taxpayer. The improvements are over
and above what the Department of Highways and Transportation would
normally do.
HUMAN RESOURCES
|
As of May 31, 2002
|
TOTAL WORKFORCE
|
% NORTHERNERS
|
| McCLEAN LAKE |
|
COGEMA Staff
|
185 |
44% |
| Long Term Contractors |
|
|
Northern Metis Site Services
|
13 |
62% |
P.A.D.C.
|
16 |
80% |
| CLUFF LAKE
|
|
COGEMA Staff
|
80 |
53% |
| Long Term Contractors |
|
|
Sakitawak Development Corp
|
12 |
100% |
Beaver Foods/Clearwater Catering
|
10 |
50% |
Mudjatik Thyssen Mining
|
29 |
34% |
|